Ensuring that Wisconsin businesses and people have the power they need when they need it is a top priority for American Transmission Company.

ATC is partnering with Wisconsin Public Service and Minnesota Power to build the Arrowhead-Weston transmission line to strengthen the reliability of the electric power grid in northern Wisconsin.

 

American Transmission Company LLC - © 2003

www.atcllc.com


Construction & Mitigation Plans submitted to PSC and DNR,
August 2005-September 2007

Please note, some of these documents are very large and may take several minutes to download and open in Adobe Reader.

Arrowhead-Weston: Project Documents

Chapter 30/NR103 Wetland/Waterway Application Documents

Please note, these are very large documents.

DNR Ch. 30 / WQC Permit, July 2005

Minnesota Court of Appeals Decision - In the Matter of the Exemption Application by Minnesota Power for a 345/230 kV High Voltage Transmission Line Known as the Arrowhead Project.
  • Decision

Power Line Route Details Finalized - After a nearly two-year approval process, the PSC has written the finalized order that outlines the details and route specifics of the 220-mile electric transmission line from Wausau to Duluth.
  • WPSR News Release
  • PSCW Order

Addendum to Application Filed - An addendum (PDF: 743KB / 35 pages) to the application was filed with the Public Service Commission of Wisconsin on April 25, 2000.

Application deemed "complete" by the PSCW - The 1,400-page application to build a power line from Wausau, Wisconsin to Duluth, Minnesota was deemed "complete" on December 15, 1999 by the Public Service Commission of Wisconsin (PSCW).

Application Filed - The official application for the Wausau to Duluth transmission line project was filed on Wednesday, November 10, 1999 in Madison at the Public Service Commission of Wisconsin (PSCW).

The 1400 page application includes a project overview, project schedule, description of need and a routing overview. Hard copies of the application were sent to each of the county offices and community libraries along the routes.

WRAO Recommends New Transmission Line - The Wisconsin Reliability Assessment Organization has filed a detailed report with the Public Service Commission of Wisconsin on June 14, 1999 supporting construction of a 230-mile transmission line between Duluth, Minn., and Wausau, Wis. - July 1, 1999 /PRNewswire/