Public
Service Commission of Wisconsin
PSC Sets Public Hearings on Arrowhead-
Weston Transmission Line Project
MADISON – The Public
Service Commission (PSC) has scheduled three public hearings
in early October
in areas along the proposed route of the Arrowhead-Weston transmission line
project. The PSC has also set a timeframe in September for written comment
from the public.
Citizens can provide
oral testimony or submit written testimony on the transmission line
project
at the following locations on the following dates:
| DATE |
START TIMES |
LOCATION |
| Wednesday, October 1, 2003 | 1:00 and 6:00 p.m. | Solon Springs Community Center 11523 S. Business 53 Solon Springs, Wisconsin |
| Thursday, October 2, 2003 | 11:00 a.m. and 6:00 p.m. | Veterans Memorial Association 608 Summit Avenue Ladysmith, Wisconsin |
| Friday, October 3, 2003 | 11:00 a.m. and 3:00 p.m. | Rib Mountain Municipal Center 3700 N. Mountain Road Wausau, Wisconsin |
In addition to receiving
oral and written testimony at the public hearings, the PSC also set
a time period
from September 16-24 where public testimony on the Arrowhead-Weston
transmission
line project can be submitted to the PSC in writing. This is another way for
interested citizens who are unable to attend the public hearings to provide
testimony on the
transmission line project. Written testimony should include
the person’s name and address and
can be sent by mail between September 16-24
to:
Jim Lepinski, Docket Coordinator
Public Service Commission of Wisconsin
P.O. Box 7854
Madison, Wisconsin 53707-7854
Technical
hearings on the Arrowhead-Weston transmission line project are slated to
begin
September 16, 2003 in Madison. The applicants, intervenors and other parties
will address
the technical aspects of the transmission line project at the technical
hearings.
The
testimony from the public hearings, the public’s written testimony and the technical
hearings will be part of the record that is developed for the Commission to
review as it considers
all the different aspects of the Arrowhead-Weston transmission
line project. Due to the judicial
nature of the proceedings, parties’ attorney
will have an opportunity to review and object to the
written testimony before
it is included in the record.
In October
2001, the Commission approved the application from the American
Transmission
Company, Wisconsin Public Service and Minnesota Power to construct a 210-mile
345 kilovolt transmission line linking the Arrowhead substation near Duluth,
Minnesota with the
Weston substation near Wausau, Wisconsin.
The Commission
reopened the case in December 2002 after receiving a revised cost
estimate from
the applicants. In the reopened case, the Commission decided to focus on the
following issues:
- Cost estimates for Arrowhead-Weston and four other extra high voltage
transmission line alternatives identified in the 1999 Wisconsin Reliability
Assessment Organization report and the Commission record for this case.
- Other cost-effective and technically feasible solutions that would resolve the
reliability concerns that were identified in the Arrowhead-Weston case.
- Cost benefit analysis on whether Arrowhead-Weston continues to be a reasonable
choice compared with other identified solutions.
(END)