| 
Construction of the Arrowhead-Weston line was completed in November 2007, seven months ahead of schedule. It has been nearly 10 years since this project was submitted to the PSC for approval.
Construction Schedule
Spread |
Completion date |
Weston to Wien |
12/27/2006 |
Wien to Longwood |
9/8/2006 |
Longwood to Chippewa |
6/19/2006 |
Chippewa to Bass Lake |
10/7/2006 |
Bass Lake to Stone Lake |
11/6/2006 |
Stone Lake to Minong |
7/31/2007 |
Minong to Hawthorne |
8/26/2007 |
Hawthorne to L-762 |
11/9/2007 |
L-762 to Arrowhead |
7/15/2007 |
| Line completed |
Nov. 2007
|
| Line place in service |
Feb. 2008 |
Historical Timeline
- April 15, 1999: Joint transmission line project
announced by Wisconsin Public Service and Minnesota Power.
- July 1999: Project sponsors hold 14 public
informational meetings along proposed routes. 7,000 landowners
invited. 2,500 attended.
- Sept. 17, 1999: Minnesota application submitted
to Minnesota Environmental Quality Board.
- Nov. 10, 1999: 1,400 page application is filed
at the Public Service Commission of Wisconsin.
- Dec. 15, 1999: Application is deemed complete
by the PSCW.
- August-September 2000: Evidentiary hearings
completed in Minnesota.
- November-December 2000: PSCW holds nine days
of public hearings at locations along the proposed routes.
- January 2001: Technical hearings are held
in Madison for 22 days including 52 technical witnesses.
- March 15, 2001: Minnesota portion of project
approved pending local permits.
- April 2001: American Transmission Company
becomes a co-applicant of the Arrowhead-Weston project
- June 4, 2001: Hermantown, Minn., City Council
grants approval to construct and upgrade the one-mile portion
of the transmission line and to upgrade the Arrowhead Substation
located in Hermantown.
- June 27, 2001: Duluth Planning and Zoning
Commission unanimously approves the project's special use permit.
- June 28, 2001: Midway, Minn., gives unanimous
approval to construct and upgrade the six-mile portion of transmission
line that is located in Midway.
- Aug. 17, 2001: PSCW unanimously approves construction
of the 220-mile line.
- Oct. 23, 2001: PSCW issues final order outlining
details and route specifications of the 220-mile line.
- August 2002: ATC holds community meetings throughout
the Arrowhead-Weston corridor.
- Aug. 21, 2002: Washburn County Exploratory Committee
unanimously recommends access to county land for surveying be granted.
- Aug. 26, 2002: Washburn County Highway Committee
approves surveyors' access to county land.
- Aug. 28, 2002: Washburn County Forestry Committee
approves surveyors' access to county land.
- October 2002: Surveyors begin work in Washburn County.
- Nov. 11, 2002: ATC reports increased price
tag for the Arrowhead-Weston project.
- Nov. 26, 2002: ATC files cost increase with
PSCW.
- July 2003: R.W. Beck, a consultant hired by PSC, says the cost assumptions for the project are reasonable.
- July 2003: ATC representatives file testimony in the Arrowhead-Weston case.
- July 2003: ATC holds informational open houses in Wausau, Spooner and Superior inviting public comment and questions.
- October 2003: PSC holds public hearings in Solon Springs, Ladysmith and Wausau.
- Dec. 19, 2003: PSC issues written order approving revised cost estimate of the Arrowhead-Weston transmission line project.
|
| |